TCO (Total Cost of Ownership) captures the full cost of running AI infrastructure โ€” not just GPU hardware, but power, cooling, networking, staff, facility, and amortization. TCO per GPU-hour is the metric that determines whether to build or rent, and which optimizations have the biggest impact.


1. TCO Components

TCO = CapEx (amortized) + OpEx (recurring)

CapEx:
  โ”œโ”€โ”€ GPUs                    40-50% of CapEx
  โ”œโ”€โ”€ Servers (CPU, RAM, NVMe) 15-20%
  โ”œโ”€โ”€ Networking (NICs, switches, cables) 15-20%
  โ””โ”€โ”€ Facility buildout        10-15%

OpEx (annual):
  โ”œโ”€โ”€ Power                   30-40% of OpEx
  โ”œโ”€โ”€ Cooling                 10-15% (included in PUE)
  โ”œโ”€โ”€ Facility lease/colo     15-20%
  โ”œโ”€โ”€ Staff (ops, ML eng)     15-25%
  โ”œโ”€โ”€ Software licenses        5-10%
  โ””โ”€โ”€ Maintenance/spares       5-10%

2. CapEx Breakdown

GPU Cluster Cost (1000 H100s)

ComponentPer-GPU costTotal (1000 GPUs)% of CapEx
H100 SXM 80GB$25,000-35,000$30M47%
Server chassis (DGX H100)$3,000-5,000/GPU$4M6%
CPU, RAM, NVMe per server$2,000-3,000/GPU$2.5M4%
InfiniBand NDR NICs (8/node)$1,500-2,500/GPU$2M3%
InfiniBand switches (leaf+spine)$2,000-4,000/GPU$3M5%
NVLink cables$500-1,000/GPU$0.75M1%
InfiniBand cables$500-1,000/GPU$0.75M1%
Storage (parallel FS)$1,000-2,000/GPU$1.5M2%
Racks + PDUs$500-1,000/GPU$0.75M1%
Facility buildout (if new)$5,000-15,000/GPU$10M16%
Total CapEx~$55K/GPU~$55M100%

Amortization

ComponentUseful lifeAnnual depreciation
GPUs3-5 years$6-10M/year
Servers4-5 years$1.3M/year
Networking5-7 years$0.8M/year
Facility10-15 years$0.7M/year
Total depreciation~$10M/year

3. OpEx Breakdown

Annual Operating Costs (1000 H100s)

Cost categoryFormulaAnnual cost
Power (GPUs)1000 ร— 700W ร— 8760hr ร— $0.08/kWh$4.9M
Power (overhead, PUE 1.3)GPU power ร— (PUE - 1)$1.5M
Facility lease125 racks ร— $2K/rack/month$3.0M
Staff5 SREs + 3 ML infra eng @ $250K loaded$2.0M
Network bandwidth100 Gbps internet @ $0.50/Mbps/month$0.6M
Software licensesMonitoring, schedulers, security$0.5M
Maintenance + spares5% of CapEx annually$2.75M
Insurance + misc$0.5M
Total annual OpEx~$15.75M

4. TCO Per GPU-Hour

def tco_per_gpu_hour(
    capex: float,
    annual_opex: float,
    num_gpus: int,
    amortization_years: int = 3,
    utilization: float = 0.75,
) -> float:
    """Calculate all-in cost per usable GPU-hour."""
    annual_capex = capex / amortization_years
    total_annual = annual_capex + annual_opex
    
    total_gpu_hours = num_gpus * 8760 * utilization
    return total_annual / total_gpu_hours

# 1000 H100 cluster:
cost = tco_per_gpu_hour(
    capex=55_000_000,
    annual_opex=15_750_000,
    num_gpus=1000,
    amortization_years=3,
    utilization=0.75,
)
# annual_capex = $18.3M
# total_annual = $34.1M
# usable GPU-hours = 1000 ร— 8760 ร— 0.75 = 6.57M hours
# TCO per GPU-hour = $5.19

# Compare to cloud:
# H100 on-demand: ~$12.29/GPU-hr
# H100 reserved 3yr: ~$5.25/GPU-hr
# โ†’ Owned at 75% utilization is competitive with 3yr reserved

Utilization Sensitivity

UtilizationOwn TCO/GPU-hrCloud reservedCloud wins?
50%$7.78$5.25Cloud wins
65%$5.98$5.25Close
75%$5.19$5.25Own wins slightly
85%$4.58$5.25Own wins clearly
95%$4.10$5.25Own wins significantly

Breakeven utilization: ~70% for 3-year amortization against reserved instances.


5. Worked Example: 1000 H100 Cluster, 3-Year TCO

Year 0 (Procurement + Setup):
  Hardware purchase:      $45M
  Facility buildout:      $10M
  Setup labor:            $1M
  โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€
  Total CapEx:            $56M

Annual Operating (Years 1-3):
  Power:                  $6.4M/yr
  Facility lease:         $3.0M/yr
  Staff:                  $2.0M/yr
  Maintenance + spares:   $2.75M/yr
  Software + network:     $1.1M/yr
  Insurance + misc:       $0.5M/yr
  โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€
  Annual OpEx:            $15.75M/yr

3-Year TCO:
  CapEx:                  $56.0M
  OpEx (3 years):         $47.25M
  โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€
  Total 3-Year TCO:       $103.25M
  Per GPU:                $103,250
  Per GPU-hour (75% util): $5.24

Cloud comparison (3yr reserved, same 1000 GPUs):
  $5.25/GPU-hr ร— 1000 ร— 8760 ร— 3 = $138M
  
  Own saves: $35M (25%) over 3 years
  But: Cloud has zero upfront cost and flexibility to scale down

6. Hidden TCO Factors

FactorImpactOften missed?
GPU failure rate (2-5%/year)Replacement cost + downtimeYes
Firmware/driver updatesDowntime for rolling updatesYes
Power price increases5-10% annual in many regionsSometimes
GPU depreciation curveResale value drops 50% after 2 yearsSometimes
Opportunity cost of CapEx$56M could be invested elsewhereYes
Scaling delay3-6 months to add capacity vs minutes in cloudYes

Self-Check

  • Break down CapEx into GPU, server, networking, and facility components
  • Calculate annual OpEx including power, cooling, staff, and maintenance
  • Compute TCO per GPU-hour at different utilization levels
  • Find the break-even utilization point between owned and cloud infrastructure
  • List hidden TCO factors that are commonly underestimated